Permit, License, or Certification Title | A description of the application process | Any changes to the process in the past 12 months | Estimated time to determine whether an application is complete
| Estimated time to for the unit to make a determination on the application
| Estimated time required to complete the application |
Annual permit or inspection fee for: | | | | | |
Milk Producer | New Applicants: 1. The applicant submits a new license application via mail with payment. 2. The application is reviewed by Permits & Licensing (P&L) and the payment is processed. 3. The Center Section Head reviews the application and assigns a regional sanitarian for field evaluation (if required). 4. The Sanitarian conducts the inspection and the Section Head approves the application. 5. P&L issues the license and mails the license to the applicant.
Renewals: 1. The applicant submits a renewal paper application via mail with payment. 2. The application is reviewed by Permits & Licensing (P&L) and the payment is processed. 3. The Center Section Head approves the application. 4. P&L issues the license and mails the license to the applicant. ** Please NOTE: Milk Producer Applications do not expire, and therefore, they do not receive renewal applications.
| None | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Bobtailer | None | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Bulk milk hauler/sampler | None | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes
|
Certified industry dairy farm inspector | None | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Distribution station | None | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Farmstead cheese processor | None | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Milk processor | None | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Milk tank truck cleaning facility | None | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Milk transportation company | None | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Milk tank truck | None | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Receiving station | None | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Transfer station | None | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Annual license fee for:
| Description of the application process
| Any changes to the process in the past 12 months
| Time to determine whether an application is complete
| Time for the unit to make a determination on the application
| Estimated time required to complete the application
|
Food processing plants: | New Applicants: 1. The applicant submits a plan review application with payment via mail and the architectural plans, HACCP, Process, etc. are submitted via email - if applicable. 2. A comment letter is sent to the applicant. Once response is received and satisfies reviewers concerns, preopening inspection (if applicable) is scheduled 3. Upon a passed preopening inspection, an approval letter is sent to the applicant stating they are approved to apply for a specified license. 4. The applicant submits an application for a license with payment via mail. 5. Permits & Licensing (P&L) reviews the application and the payment is processed. 6. Once the application is approved by the designated officer (Section Head or Shellfish Standardization Officer), the license is issued and mailed to the applicant.
Renewals: 1. The applicant submits a paper application via mail with payment. 2. The application is reviewed by P&L and the payment is processed. 3. The license is issued and mailed. | None | | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Bakery plant | None | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Cannery | None | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Charity deer processing plant | None | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Civic or nonprofit organization | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Confectionary plant | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Crab meat plant | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Ice manufacturing plant | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Shellfish: Shucking, packing, or repacking plant | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Shellfish: Shipping or reshipping plant | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Shellfish: Seasonal shellstock shipping or reshipping plant | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Food manufacturing plant | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
A food warehouse or distribution center that distributes: Potentially hazardous food | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
A food warehouse or distribution center that distributes: Only non-potentially hazardous food | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Bottled water plant | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Soft drink manufacturing plant | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Frozen food manufacturing plant | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Seasonal food manufacturing plant | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
On-farm home processing plant | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Producer mobile farmer’s market unit | None. | 2-3 weeks | within 30 days | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Frozen dessert mix or frozen dessert plant with manufacturing capacity of: | None. | | | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
0-25,000 gallons | None. | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
25,001-100,000 gallons | None. | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
100,001-250,000 gallons | None. | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
250,001-500,000 gallons | None. | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes |
Over 500,000 gallons | None. | < 1 week | < 1 month | New: 10 -15 minutes to fill out application; collection of documentation is dependent on applicant and time can vary Renewal: 10-15 minutes
|